wpff6da177.png
wp3658cd5e.png

Jones & Sons successfully apply for numerous Natural England Licences every year.

 

Specific licence issues are dealt with under the Protected Species section of these web pages.

 

There are important features to Licence Application which need to be understood. The most important of these is correct timing within the overall management structure of the proposed development. It is imperative that the issues of protected species are take onboard at the inception of the project, failure to do this can add significant delays to the proposed timetable of the project.

 

The general path of licence application is:

 

Survey (frequently only possible for part of the year depending on species)

 

An appropriate mitigation and compensation scheme designed

 

Planning Permission granted (if required)

 

Applying for the Licence (can take 40 + working days)

 

Acting on the Mitigation recommendations of the Licence (can have annual timing issues depending on species).

 

21-23 North Road, Hertford, Hertfordshire SG14 1LN - Tel: 01992 552407, mail: reception@jonesandsons.co.uk